Timeline

 
  • Final design

    Though April 2021
  • Site development permit

    Through April 2021

    City of Beaverton permitting process

  • Right-of-way acquisition

    October 2020-August 2021

    Dates subject to change

  • Regulatory permits

    January-August 2021

    U.S. Corp of Engineers and Department of State Lands permitting processes

  • Bid

    August 2021

    Date subject to change

  • Construction

    September 2021-December 2022